Streets under construction in Fountain Hills

Paving to begin this month

The Town of Fountain Hills is pushing forward in street management, with four streets scheduled for pavement this month. 

From Oct. 12-14, crews will be adjusting utilities, and old asphalt will be removed Oct. 22-23 before new asphalt will be laid Oct. 26-30, according to the town.

North Bluejay Place is scheduled for pavement on Oct. 26, followed by North Tamarack Lane on Oct. 27, East Bradford Drive on Oct. 28 and North Mayflower Drive on Oct. 29. Crews have added Oct. 30 as a backup weather day, if needed. 